A. Construction Linked Plan
I. Jaypee Chambers 1 A (Lobby + 11)
S. No | Payment Due |
Percentage (%) of BSP |
Other Charges |
1 |
On Booking along with application form |
10% of BSP |
|
On or within 1 month from the date of | |||
2 |
issuance of PAL |
10% of BSP |
|
On or within 3 months from the date of | |||
3 |
issuance of PAL |
10% of BSP |
|
4 |
On completion of excavation |
5% of BSP |
Car Parking* |
5 |
On laying of upper basement slab |
5% of BSP |
E DC |
6 |
On laying of 2nd floor roof slab |
10% of BSP |
ID C |
7 |
On laying of 4th floor roof slab |
10% of BSP |
|
8 |
On laying of 6th floor roof slab |
10% of BSP |
|
9 |
On laying of 8th floor roof slab |
10% of BSP |
|
10 |
On laying of 10th floor roof slab |
5% of BSP |
ESSC |
11 |
On laying of to p floor roof slab |
5% of BSP |
|
12 |
On completion of internal plaster & flooring |
5% of BSP |
|
Provisional Com mon | |||
area maintenance | |||
advance + IFMD + | |||
13 |
On offer of Possession |
5% of BSP |
One time lease rent |
Total |
100% |
*Additional Car parking will be charge d on the completion of excavation, if opted at the time of booking.
Cheques should be drawn in favor of ‘Jaiprakash Associates Limited’ Notes:
- Installments under S. No. 412 may run concurrently with those under S. No . 1 3 based on the physical progress of Work at site.
- The Demand Letter for Installments at S. No. 4 to 12 shall be sent in advance providing for payment period of up to 15 days.
II. Jaypee Chambers 1 B (Lobby + 23)
S. No | Payment Due |
Percentage (%) of BSP |
Other Charges | |
1 |
On Booking along with application form |
10% of BSP |
||
On or within 1 month from the date of | ||||
2 |
issuance of PAL |
10% of BSP |
||
On or within 3 months from the date of | ||||
3 |
issuance of PAL |
10% of BSP |
||
4 |
On completion of excavatio n |
5% of BSP |
Car Parking* | |
5 |
On laying of upper basement slab |
5% of BSP |
E DC | |
6 |
On laying of 3rd floor roof slab |
10% of BSP |
ID C | |
7 |
On laying of 6th floor roof slab |
10% of BSP |
||
8 |
On laying of 9th floor roof sl ab |
10% of BSP |
||
9 |
On laying of 12th floor roof slab |
5% of BSP |
||
10 |
On laying of 15th floor roof slab |
5% of BSP |
ESSC | |
11 |
On laying of 18th floor roof slab |
5% of BSP |
||
12 |
On laying of to p floor roof s lab |
5% of BSP |
||
13 |
On completion of internal plaster & flooring |
5% of BSP |
||
Provisional Com mon | ||||
area maintenance | ||||
advance + IFMD + | ||||
14 |
On offer of Possession |
5% of BSP |
One time lease rent | |
Total |
100% |
Cheques should b e drawn in favor of ‘Jaiprakash Associates Limited’
Notes:
1. Installments under S. No . 4 13 may run concurre ntly with tho se under S. No. 1 3 based on the physical progress
of Work at site.
2. The Demand Letter for Installments at S. No. 4 to 13 shall be sent in advanc e providing for payment period of up
to 15 days.
B. Down Payment Plan
S. No |
Payment Due |
Percentage (%) o f BSP |
Other Charges |
|
1 |
On Booking along with application |
10% of BSP |
||
form | ||||
2 |
On or within 1 month from the |
85% of BSP |
IDC + EDC+ Car park* + Elec tric |
|
date of issuance of PAL |
substation charges |
|||
I FMD + Provisional Common |
||||
3 |
On offer of possession |
5% of BSP |
area maintenance advance + |
|
One time lease rent |
||||
TOTAL |
100% |
Note : Down paym ent discount up to 15%, based on the stage of cons truction at t he time of issuance of PAL *Additional Car parking w ill be charge d along with car park charges, if opted at the time of booking.
C. Partial Down Payment Plan
S. No |
Payment Due |
Percentage (%) of BSP |
Other Charges |
|
1 |
On Booking along with application |
10% of BS P |
||
form |
||||
2 |
On or within 1 month from the date |
45% of BS P |
IDC + Car par k* + ESSC + E DC |
|
of issuance of PAL |
||||
3 |
On laying of upp er basement slab |
20% of BS P |
||
4 |
On laying of 7th floor roof sl ab |
20% of BS P |
||
IFMD + Provisional Common |
||||
5 |
On offer of possession |
5% of BSP |
area maintenance advance + |
|
One time Lease Rent |
||||
TOTAL |
100% |
Note : Partial Down payment is count up to 11%, based on the stage of construction at the time of issuance of PAL *Additional Car parking w ill be charge d along with car park charges, if opted at the time of booking.